Offline Facility
Offline (2025)Zaporizhstal
Select a material to see offline facilities, capacity gap, alternatives, and rerouting delay.
Data from public 2025 annual reports (Metinvest, Rosneft, WB) and CSCMP logistics benchmarks.
Zaporizhstal
~4M tons/yr offline
Partial coverage โ gap remains ~2M tons/yr
Combined spare: ~2M tons/yr
Rerouting benchmark: 2โ6 weeks (CSCMP industry-typical range โ not an incident-specific prediction)
Coverage expands as new public disclosures are published. Bookmark this page and check before each procurement cycle.
| Material | Offline Facility | Capacity Offline | Regional Share | Alternatives | Combined Spare | Rerouting Benchmark |
|---|---|---|---|---|---|---|
| Hot-rolled coil (rebar feedstock) | Zaporizhstal | ~4M tons/yr | ~40% | MMK + NLMK | ~2M tons/yr | 2โ6 weeks |
| HDPE | Tobolsk-Polymer (partial) | ~300K tons/yr | ~12% | Sibur (Kazan, Tomsk) | ~180K tons/yr | 3โ8 weeks |
| Diesel | Ryazan Refinery (partial) | ~5M tons/yr | ~8% | Rosneft (other sites), Lukoil | ~2M tons/yr | 1โ4 weeks |
| Wooden pallets | Vologda Les (offline) | ~1.2M units/yr | ~15% | Arkhangelsk, Kostroma clusters | ~0.7M units/yr | 4โ10 weeks |